Kamoa-Kakula Copper Project kicking ahead of Schedule | DRC
In addition, at the mine’s high-capacity 2,000-tonne-per-hour ore conveyor system at the Kakula North declines, final commissioning is currently underway with operations to begin soon.
“Once this happens, the ore mined in the northern portion of the Kakula Mine will be combined and be placed on a blended surface stockpile,” he said. “The Kakula South and Kansoko declines are not equipped with conveyor systems; as such, the ore mined from these deposits will continue to be placed on separate surface stockpiles, based on copper grades.”
At this point, the mine’s surface stockpiles contain about 116,000t of ore grading 6.08% copper, plus 446,000t grading 2.73% copper; this includes satellite stockpiles at Kakula South and Kansoko.
Structural steel and equipment for the mine’s processing plant are next on the list; more than 300 truckloads of supplies are to be delivered before the end of this month. The facility’s two ball mills, each measuring 9.75m (32ft) long and 6.1m (20ft) in diameter have been completed, and the third and final shipment of components should be on-site by the end of September.
Once online, Kakula is projected to be the highest-grade major copper mine in the world, producing 3.8 million tonnes per year initially.
It is also designed to have one of the top environmental footprints in the industry across tier-one copper operations, Friedland said.
“It will be powered by clean, renewable hydroelectricity and be among the world’s lowest greenhouse gas emitters per unit of copper produced. It also will have a relatively tiny surface footprint as approximately 55% of the mine’s tailings will be pumped back into underground workings,” he said.
Kamoa-Kakula is a joint venture between Ivanhoe Mines (39.6%), Zijin Mining Group (39.6%), Crystal River Global Limited (0.8%) and the DRC government.