Ivanhoe Mines announces Kamoa-Kakula achieved record copper production of 35,856 tonnes in May  1New Mining Projects Copper Mining in DRC 

Ivanhoe Mines announces Kamoa-Kakula achieved record copper production of 35,856 tonnes in May 

Monthly copper production equivalent to annual production of approximately 430,000 tonnes 

New daily ore milling record achieved at Kamoa-Kakula, equivalent to an annual rate of approximately 9.8 million tonnes  

  

 Phase 1 and 2 concentrators continue to operate at above-design copper recoveries

 

Phase 3 expansion and smelter advancing on schedule for first production in Q4 2024

KOLWEZI, DEMOCRATIC REPUBLIC OF CONGO – Ivanhoe Mines (TSX: IVN; OTCQX: IVPAF) Co-Chairs Robert Friedland and Yufeng “Miles” Sun announced today that the Kamoa-Kakula Copper Complex in the Democratic Republic of Congo achieved a monthly production record of 35,856 tonnes of copper in concentrate during May. 

Copper production during April was 34,826 tonnes of copper in concentrate, bringing quarter-to-date production to 70,682 tonnes.

A new daily milling record of 29,366 tonnes of ore was also achieved by the Phase 1 and 2 concentrators. This is equivalent to an annual milling rate of 9.8 million tonnes per annum (after accounting for availability). This record far exceeds the increased milling capacity of 9.2 million tonnes per annum following the debottlenecking program of the Phase 1 and 2 concentrators, which was completed in February 2023. 

Average copper recoveries for the month were 87%, above the Phase 1 and 2 concentrator nameplate recovery rates. 

Construction activities for the Phase 3 expansion, including the largest copper smelter in Africa, with a capacity of 500,000 tonnes of 99+%-pure copper anodes, are advancing on schedule for first production in the fourth quarter of 2024.

Watch a June 2023 video of operations and construction activities at Kamoa-Kakula: https://vimeo.com/833031454/fb6ea4e192  

Ivanhoe Mines announces Kamoa-Kakula achieved record copper production of 35,856 tonnes in May  2

 

Concrete foundations for the two ball mills of the Phase 3 concentrator on the left, with foundations for the flotation cells on the right. The first batch of ball mill foundation steel is expected at site later this month. The first ball mill, supplied by CITIC Heavy Industries of Luoyang, China, also is expected to be delivered later this month.

Ivanhoe Mines announces Kamoa-Kakula achieved record copper production of 35,856 tonnes in May  3

Concrete foundations for the Phase 3 concentrator tailings thickener. Over 60% of concrete has been poured to date and approximately 6,000 tonnes of the required 7,100 tonnes of structural steel have been fabricated, 50% of which has been shipped to site. 

Ivanhoe Mines announces Kamoa-Kakula achieved record copper production of 35,856 tonnes in May  4

Steel erection of Kamoa-Kakula’s direct-to-blister flash furnace and the electric slag cleaning furnace. Overall smelter construction is now approximately 50% complete. Fabrication of the anode furnaces, ball mill and SAG mill, also manufactured by CITIC Heavy Industries, is complete with shipping expected imminently. 

Ivanhoe Mines announces Kamoa-Kakula achieved record copper production of 35,856 tonnes in May  5

Construction of new on-site accommodation. There are approximately 14,000 employees and contractors at site; approximately 97% of Kamoa’s employees are Congolese.

Ivanhoe Mines announces Kamoa-Kakula achieved record copper production of 35,856 tonnes in May  6

Loading

Share this article on

Related posts

You have successfully subscribed to the newsletter

There was an error while trying to send your request. Please try again.

Copperbelt Katanga Mining will use the information you provide on this form to be in touch with you and to provide updates and marketing.