KakulaCobalt Copper Mining in DRC 

Ivanhoe’s Kakula mine development advances ahead of schedule

Kamoa-Kakula mine in the DRC. (Image courtesy of Ivanhoe Mines).

The company reported that more than 13.5 kilometres (8 miles) of underground development is now completed, 4.2 kilometres (3 miles) ahead of schedule.

“The mining team is on pace to set a new monthly development record of 1.7 kilometres of advancement ─ 562 metres ahead of plan for the month,” the company said in a release.

Ivanhoe said each blast in Kakula’s high-grade mining zone produces approximately 550 tonnes of ore.

KAKULA’S HIGH-GRADE ORE STOCKPILE IS EXPECTED TO TOTAL APPROXIMATELY 1.5 MILLION TONNES PRIOR TO THE START OF INITIAL PRODUCTION

Kakula’s high-grade ore stockpile is expected to total approximately 1.5 million tonnes prior to the start of initial production.

According to the pre-feasibility study (PFS) released last year, if all phases are completed the Kamoa-Kakula project is expected to reach peak annual production of more than 700,000 tonnes of copper.

The mining company also announced cost-saving measures that should cut costs by about $75 million, including lower expenditures this year at its Platreef palladium-platinum-nickel-copper-gold-rhodium project in South Africa and at its Kipushi zinc-copper-lead-germanium mine in the DRC.

Work on Platreef’s first shaft will continue, but the company has reduced the project’s 2020 budget to $41.7 million, down from $60 million, and trimmed its budget for Kipushi to $28.7 million, down from $40 million.

The company also announced voluntary salary reductions by senior management of up to 35% for a six-month period, and the suspension of all short-term incentive award payments for 2020.

In addition, Ivanhoe has trimmed its corporate and senior management headcount and reduced its footprint of global offices.

The company’s head office will remain in South Africa and be supported by satellite offices in Beijing and London.

In terms of management changes, Egizio Bianchini, Ivanhoe’s executive vice chairman, will relinquish his executive role but remain as vice chairman and a director.

The initiatives “are designed to further build on our robust cash and cash equivalents of approximately $600 million and essentially no debt,” Marna Cloete, the company’s CEO said.

Andrew Mikitchook of BMO Capital Markets has an outperform rating on the stock and a price target of $9.00 per share, according to The Northern Miner.

At presstime in Toronto the company’s shares were trading at $2.69 apiece within a 52-week trading range of $1.80 and $4.54.

“The company is in a strong financial position with $603 million at the end of March with today’s press release highlighting ~$75 million in cost savings through 2021 including the reduction of activities at Platreef and Kipushi, deferral of exploration activities, and voluntary management salary reductions,” Mikitchook wrote in a research note.

“The company continues to prioritize focus towards developing Kakula on time and on budget.”


Share this article on

Related posts

One Thought to “Ivanhoe’s Kakula mine development advances ahead of schedule”

  1. I want a job I was doing power electrical engineering level1
    danielbanda233@gmail.com

Comments are closed.

You have successfully subscribed to the newsletter

There was an error while trying to send your request. Please try again.

Copperbelt Katanga Mining will use the information you provide on this form to be in touch with you and to provide updates and marketing.