Kamoa-Kakula Copper Project mines 269,000 tonnes of ore from the Kakula and Kansoko mines in December at an average grade of 5.36% copper 1Mining in DRC Copper 

Kamoa-Kakula Copper Project mines 269,000 tonnes of ore from the Kakula and Kansoko mines in December at an average grade of 5.36% copper

Ivanhoe Mines (TSX: IVN; OTCQX: IVPAF) Co-Chairs Robert Friedland and Yufeng “Miles” Sun are pleased to announce that underground development at the Kamoa-Kakula Copper Project in the Democratic Republic of Congo (DRC) mined and stockpiled 269,000 tonnes of ore grading 5.36% copper in December from the Kakula and Kansoko mines, including 55,000 tonnes grading 8.75% copper from the high-grade centre of the Kakula Mine. The tonnage was 7.6% higher than November, while the copper grade was 10.5% higher.

The project’s pre-production surface stockpiles now contain approximately 1.52 million tonnes of high-grade and medium-grade ore at an estimated blended grade of 4.03% copper. Contained copper in the stockpiles increased by approximately 14,400 tonnes in December – a 30.9% increase over November’s production reflecting the increased mining in the ultra-high-grade centre of the Kakula Deposit – to a cumulative total of more than 61,000 tonnes.

Kamoa-Kakula Copper Project mines and stockpiles 269,000 tonnes of ore from the Kakula and Kansoko mines in December, at an average grade of 5.36% copper, including 55,000 tonnes grading 8.75% copper from the high-grade centre of the Kakula Mine

Pre-production ore stockpiles now hold 1.52 million tonnes grading 4.03% copper, containing more than 61,000 tonnes of copper

Record underground development of 2,792 metres completed in December; more than 29.8 kilometres now complete – 10.5 kilometres ahead of plan

Remarkable thickness of the high-grade copper ore in the centre of the Kakula Mine has allowed the expansion of development drifts in this area to 10 metres high by 7.5 metres wide (75 square metres).

Overall progress of Kamoa-Kakula’s first phase, 3.8-Mtpa mining and milling operation now approximately 68% complete; first copper concentrate production continues on track for July 2021

Loading

Share this article on

Related posts

You have successfully subscribed to the newsletter

There was an error while trying to send your request. Please try again.

Copperbelt Katanga Mining will use the information you provide on this form to be in touch with you and to provide updates and marketing.