Kamoa's 2 concentratorsCopper Mining in DRC New Mining Projects 

Kamoa-Kakula Phase 1 concentrator plant approaching steady-state-design performance

14,815 tonnes of copper produced in August, bringing the year-to-date production to more than 36,700 tonnes

Installation of an additional concentrate filter expected by end of October 2021, further boosting copper production

Phase 2 concentrator plant construction now 44% complete

Mining crews delivered 220,000 tonnes of ore grading a record 6.03% copper from August 1 to 20, including 85,000 tonnes grading 7.55% copper from the centre of the Kakula Mine

Surface ore stockpiles continue to grow; now hold 3.59 million tonnes grading 4.77% copper, containing more than 171,000 tonnes of copper

All six new turbines at the Mwadingusha hydropower plant now operational and generating clean electricity for Kamoa-Kakula

Kolwezi, Democratic Republic of Congo–(Newsfile Corp. – September 7, 2021) – Ivanhoe Mines (TSX: IVN) (OTCQX: IVPAF) Co-Chairs Robert Friedland and Yufeng “Miles” Sun are pleased to announce that hot commissioning and ramp-up of Kamoa-Kakula’s Phase 1, 3.8 million-tonne-per-annum (Mtpa) concentrator plant is progressing well and approaching nameplate steady-state-design performance.

During August, the plant achieved an average milling rate of more than 9,000 tonnes per day at an average feed grade of more than 6.0% copper. On August 29, the Phase 1 concentrator plant produced in excess of 600 tonnes of copper in filtered concentrate, which is the plant’s steady-state-design daily production rate.

During August, the concentrator plant produced concentrate containing 14,815 tonnes of copper. As of August 31, a total of 36,712 tonnes of copper had been produced year-to-date for delivery to either the Lualaba Copper Smelter near Kolwezi, or to international markets. All concentrate produced to date has been loaded onto trucks (either bulk for the Lualaba Smelter or in bags for international markets) and the concentrate backlog at the mine site has been cleared.

Cannot view this image? Visit: https://i0.wp.com/orders.newsfilecorp.com/files/3396/95693_59685641249988fc_002.jpg?w=640&ssl=1



Chart 1: Monthly tonnes of copper produced May 2021 to August 2021.

Steve Amos, Kamoa Copper’s Head of Projects, commented, “The hot commissioning and ramp-up of the Phase 1 concentrator plant is going very well, with no significant issues encountered to date. Fast tracking of an additional concentrate filter will enable us to produce more concentrate and take advantage of the exceptional ore grades coming from the Kakula Mine, as well as any additional milling throughput in excess of design capacity. A third concentrate filter is being procured and will be incorporated into the Phase 2 plant.”

Copper recoveries improved to an average of 83% during August, with recoveries in excess of 86% achieved on multiple occasions. The Phase 1, steady-state-design copper recovery is approximately 86%.

Cannot view this image? Visit: https://i0.wp.com/orders.newsfilecorp.com/files/3396/95693_59685641249988fc_003.jpg?w=640&ssl=1



Chart 2: Cumulative tonnes of copper produced May 2021 to August 2021.

Ivanhoe’s production guidance for contained copper in concentrate at Kamoa-Kakula in 2021 is 80,000 to 95,000 tonnes. The figures are on a 100%-project basis and metal reported in concentrate is prior to refining losses or deductions associated with smelter terms. The guidance assumes ramp-up from first production continues in line with published technical disclosures.

Daily concentrate grades in excess of the steady-state-design grade of approximately 57% copper also have been achieved on several occasions, with the monthly average exceeding 48% copper. The current focus of the commissioning team is on balancing and optimizing the flotation and regrind milling areas. This work is expected to further improve the consistency of concentrate grade and copper recoveries.

Commissioning and operation of the concentrator plant’s regrind mills is well underway. The regrind mills are the final pieces of equipment to be commissioned in the Phase 1 concentrator.

Kamoa-Kakula is fast tracking the installation of an additional concentrate filter, which already has been delivered to the mine site, to be able to take advantage of copper feed grades and milling rates in excess of design parameters. The additional concentrate filter is expected to be installed by the end of October 2021, enabling the Phase 1 concentrator to produce more copper than its design capacity of approximately 200,000 tonnes per year.

Cannot view this image? Visit: https://i0.wp.com/orders.newsfilecorp.com/files/3396/95693_59685641249988fc_004.jpg?w=640&ssl=1

In early August, Ben Munanga, Kamoa Copper’s Chairman (right), welcomed Princess Adèle Kayinda Mahina, the Democratic Republic of Congo’s Minister of Portfolio, to the Kamoa-Kakula Copper Project. The DRC government’s 20% interest in the Kamoa-Kakula Copper Project is managed by the Portfolio Ministry.

Cannot view this image? Visit: https://i0.wp.com/orders.newsfilecorp.com/files/3396/95693_59685641249988fc_005.jpg?w=640&ssl=1

Princess Adèle Kayinda Mahina (left) and Marna Cloete, Ivanhoe’s President and CFO, inside a scooptram bucket during an underground visit of the Kakula Mine.

Cannot view this image? Visit: https://i0.wp.com/orders.newsfilecorp.com/files/3396/95693_59685641249988fc_006.jpg?w=640&ssl=1



Pouring Kamoa Copper blister ingots, containing approximately 99% copper, at the Lualaba Copper Smelter near Kolwezi, Democratic Republic of Congo.

Cannot view this image? Visit: https://i0.wp.com/orders.newsfilecorp.com/files/3396/95693_59685641249988fc_007.jpg?w=640&ssl=1



An electronic chip affixed to a Kamoa Copper blister copper ingot for tracking and security.

Phase 2 overall project 44% complete, with civil works effectively complete and structural steel, mechanical, piping and platework (SMPP) erection and installation well underway

Construction of the second 3.8-Mtpa concentrator plant (Phase 2) is progressing well, with the overall project 44% complete; engineering and procurement activities are nearing completion. Civil construction works also is nearing completion with the focus now on erection of structural steel and the installation of platework and equipment. The primary and secondary ball mill discharge sumps, as well as the mill base plates, are being installed; mill installation is on the critical path. SMPP construction is on-going in all areas.

Deliveries of structural steel, platework and mechanical equipment continue daily with more than 321 truckloads already delivered to site and another 126 en-route. Manufacturing of all long-lead items of equipment now is complete with several items already delivered to site and the remainder en-route. The final major contract for electrical, control and instrumentation (EC&I) supply and installation, has been awarded. The Phase 2 concentrator remains on track for completion in Q3 2022.

Cannot view this image? Visit: https://i0.wp.com/orders.newsfilecorp.com/files/3396/95693_59685641249988fc_008.jpg?w=640&ssl=1



Lifting the Phase 2 flotation conditioning tank into position.

Cannot view this image? Visit: https://i0.wp.com/orders.newsfilecorp.com/files/3396/95693_59685641249988fc_009.jpg?w=640&ssl=1



The Phase 2 concentrator plant under construction in the foreground, with the operating Phase 1 concentrator plant in the background.

Cannot view this image? Visit: https://i0.wp.com/orders.newsfilecorp.com/files/3396/95693_59685641249988fc_010.jpg?w=640&ssl=1



The side-by-side Phase 1 and Phase 2 concentrator plants

Cannot view this image? Visit: https://i0.wp.com/orders.newsfilecorp.com/files/3396/95693_59685641249988fc_011.jpg?w=640&ssl=1



Chen Hong Tao (left) and Wang Pengfei installing the Phase 2 flotation base plates.

Cannot view this image? Visit: https://i0.wp.com/orders.newsfilecorp.com/files/3396/95693_59685641249988fc_012.jpg?w=640&ssl=1



Shells for the Phase 2 ball mills arriving at Kamoa-Kakula.

Cannot view this image? Visit: https://i0.wp.com/orders.newsfilecorp.com/files/3396/95693_59685641249988fc_013.jpg?w=640&ssl=1



Installation of the second Larox concentrate filter press, manufactured by Outotec, of Finland.

Cannot view this image? Visit: https://i0.wp.com/orders.newsfilecorp.com/files/3396/95693_59685641249988fc_014.jpg?w=640&ssl=1

Mechanic Gretta Lusa Ngoie repairing a wheel at the Kakula Mine.

Mining continues ahead of schedule, adding to the surface ore stockpiles

An alignment of reporting dates for the mines and the concentrator has resulted in a truncated reporting period this month, from August 1 to 20. A total of 220,000 tonnes grading 6.03% copper was mined during this shortened period, and comprised 204,000 tonnes grading 6.16% copper from the Kakula Mine, including 85,000 tonnes grading 7.55% copper from the mine’s high-grade centre, and 16,000 tonnes grading 4.31% copper from the Kansoko Mine. For the month-long period from July 21 to August 20, 378,000 tonnes was mined grading 5.82% copper, a portion of which was included in last month’s total.

The project’s surface stockpiles now contain approximately 3.59 million tonnes of high-grade and medium-grade ore at an estimated, blended average of 4.77% copper. Contained copper in the stockpiles at the end of August now totals more than 171,000 tonnes (the current copper price is approximately US$9,400 per tonne).

As the plant ramps up to full Phase 1 design capacity, and the mine toward Phase 2 production capacity, the surface stockpiles are expected to continue to build at a reduced rate.

Surface ore stockpiles total 3.59 million tonnes grading 4.77% copper

Cannot view this image? Visit: https://i0.wp.com/orders.newsfilecorp.com/files/3396/95693_59685641249988fc_015.jpg?w=640&ssl=1



Chart 3: Cumulative tonnes and grade of ore stockpiles at the Kakula and Kansoko mines – May 2020 to August 2021.

Cannot view this image? Visit: https://i0.wp.com/orders.newsfilecorp.com/files/3396/95693_59685641249988fc_016.jpg?w=640&ssl=1


Chart 4: Growth in contained copper in ore stockpiles at the Kakula and Kansoko mines – May 2020 to August 2021.

Cannot view this image? Visit: https://i0.wp.com/orders.newsfilecorp.com/files/3396/95693_ivanhoe1_550.jpg?w=640&ssl=1



Aerial view of the Kakula Mine, concentrator plant and accommodations with the main stockpiles at Kakula’s northern declines (in red circle). The blended stockpiles currently contain approximately 1.76 million tonnes grading 5.03% copper.

Cannot view this image? Visit: https://i0.wp.com/orders.newsfilecorp.com/files/3396/95693_ivanhoe2_550.jpg?w=640&ssl=1



Aerial view of the Kakula south decline and ore stockpiles containing a combined 1.34 million tonnes grading 4.77% copper (consisting of 663,000 high-grade tonnes @ 6.14% copper and 682,000 medium-grade tonnes @ 3.44% copper).

Cannot view this image? Visit: https://i0.wp.com/orders.newsfilecorp.com/files/3396/95693_ivanhoe3_550.jpg?w=640&ssl=1



Aerial view of the Kansoko Mine and ore stockpiles containing a combined 485,000 tonnes grading 3.83% copper (consisting of 142,000 high-grade tonnes @ 5.88% copper and 343,000 medium-grade tonnes @ 2.98% copper).

Cannot view this image? Visit: https://i0.wp.com/orders.newsfilecorp.com/files/3396/95693_59685641249988fc_031.jpg?w=640&ssl=1

 

Figure 1: Underground development completed at Kakula Mine to August 30, 2021 (in black).

Kakula is projected to be the world’s highest-grade major copper mine, with an initial mining rate of 3.8 Mtpa at an estimated, average feed grade of more than 6.0% copper over the first five years of operations, and 5.9% copper over the initial 10 years of operations. Phase 1 is expected to produce approximately 200,000 tonnes of copper per year, while the Phase 2 expansion is forecast to increase production to approximately 400,000 tonnes of copper annually. The project is on track to complete the Phase 2 expansion in Q3 2022. Based on independent benchmarking, the project’s phased expansion scenario to 19 Mtpa would position Kamoa-Kakula as the world’s second-largest copper mining complex, with peak annual copper production of more than 800,000 tonnes.

The Kamoa-Kakula Copper Project is a joint venture between Ivanhoe Mines (39.6%), Zijin Mining Group (39.6%), Crystal River Global Limited (0.8%) and the Government of the Democratic Republic of Congo (20%). A 2020 independent audit of Kamoa-Kakula’s greenhouse gas intensity metrics performed by Hatch Ltd. of Mississauga, Canada, confirmed that the project will be among the world’s lowest greenhouse gas emitters per unit of copper produced.

Cannot view this image? Visit: https://i0.wp.com/orders.newsfilecorp.com/files/3396/95693_59685641249988fc_034.jpg?w=640&ssl=1



Phase 2 high-pressure-grinding-rolls (HPGR) tower and green feed bin (in red circle) installed.

Hot commissioning of the backfill plant is proceeding well, with the first paste backfill delivered to the underground mining areas in August. The backfill plant will be used to mix tailings from the processing plant with cement to produce paste backfill. This backfill will be pumped back into the mine and used to help support mined-out areas. Approximately one half of the mine’s tailings will be sent back underground, significantly reducing the surface tailings storage.

Cannot view this image? Visit: https://i0.wp.com/orders.newsfilecorp.com/files/3396/95693_59685641249988fc_035.jpg?w=640&ssl=1



Kamoa Copper’s commissioning team at the backfill plant now delivering approximately 50% of the tailings to mined out areas in the Kakula Mine.

Study work underway to accelerate Phase 3 mine and concentrator expansion

Study work for the Phase 3 mine and concentrator expansion is underway, which includes optimization work to determine mining production capacity and costs at the various mining areas on the Kamoa-Kakula complex, including expanded facilities at the Kansoko Mine, Kamoa North (including the Bonanza Zone) and Kakula West.

This work also will inform the optimal sizing of the Phase 3 concentrator, which was outlined as a further expansion of 3.8 Mtpa in the Kamoa-Kakula Integrated Development Plan announced in September 2020. In addition, the studies will take into consideration the plans to upgrade turbine 5 at the Inga II hydropower complex to provide 162 megawatts of renewable hydropower, as well as the construction of a direct-to-blister smelter.

Once the optimization work is completed, Kamoa Copper will advance into a more detailed phase of design and engineering work with its objective to accelerate the Phase 3 concentrator expansion.

All six new turbines at the Mwadingusha hydropower plant now operational and generating clean electricity

All six new turbines at the Mwadingusha hydropower plant now have been synchronized to the national electrical grid, with each generating unit producing approximately 13 megawatts (MW) of power, for a combined output of approximately 78 MW.

Cannot view this image? Visit: https://i0.wp.com/orders.newsfilecorp.com/files/3396/95693_59685641249988fc_036.jpg?w=640&ssl=1



Mwadingusha powerhouse with all six generating units fully assembled and generating 78 MW of clean, sustainable electricity.

In early August, Kamoa-Kakula’s Energy company announced that it had signed an extension of the existing financing agreement with the Democratic Republic of Congo’s state-owned power company SNEL to upgrade turbine 5 at the Inga II hydropower complex. Since June 2021, rehabilitation scoping works and technical visits have been conducted by Stucky Ltd., of Renens, Switzerland, the Engineering, Procurement and Construction Management (EPCM) company. Turbine 5 is expected to produce 162 MW of renewable hydropower, providing the Kamoa-Kakula Copper Complex and associated smelter with abundant, sustainable electricity for future expansions.

Cannot view this image? Visit: https://i0.wp.com/orders.newsfilecorp.com/files/3396/95693_ivanhoe4_550.jpg?w=640&ssl=1

Engineers from Kamoa-Kakula’s Energy company, SNEL, Stucky, Voith and Zijin Mining conducting an inspection of the Inga II hydropower complex. The Congo River, Inga dam, Inga I turbines and the channel feeding water to the Inga II turbines, are circled in red.

Cannot view this image? Visit: https://i0.wp.com/orders.newsfilecorp.com/files/3396/95693_59685641249988fc_039.jpg?w=640&ssl=1



The Inga II electrical substation and transmission lines.

Kamoa Copper partnership continues COVID-19 vaccination efforts for employees and residents who live in host communities

Kamoa-Kakula has successfully focused on prevention, preparation, and mitigation in managing the risks associated with COVID-19. Large-scale testing, combined with focused preventative measures, ensured that positive cases were quickly identified, isolated, and treated, with cross contamination kept to a minimum. Maintaining this high standard of risk management remains the main focus to prevent future cases.

With the support of the Democratic Republic of Congo government, UNICEF and other stakeholders, Kamoa Copper SA completed its first round of COVID-19 vaccinations on June 24, 2021. In conjunction with the DRC government’s extended program of vaccinations, the second round of COVID-19 vaccinations at Kamoa-Kakula commenced in mid-August. The vaccine will be available for all Kamoa Copper employees, contractors and residents living in the mine’s host communities.

The Kamoa COVID-19 hospital continues to treat patients when required, as construction progresses well for the expansion and upgrade of the primary healthcare wing. Kamoa-Kakula’s highly experienced medical team applies the latest medical treatments, supported by a world-leading emergency response and paramedic team.

As the pandemic evolves, the medical team at the Kamoa hospital continues to review and update risk mitigation protocols, while ensuring that new medical advances are investigated and applied to protect the health and safety of employees and community members.

Cannot view this image? Visit: https://i0.wp.com/orders.newsfilecorp.com/files/3396/95693_59685641249988fc_040.jpg?w=640&ssl=1



Danielle Morton, Kamoa Copper Reliability Engineer, holding her vaccination certificate after receiving her second vaccination dose.

Cannot view this image? Visit: https://i0.wp.com/orders.newsfilecorp.com/files/3396/95693_59685641249988fc_041.jpg?w=640&ssl=1



Celestin Kazeu Kushinga at the Kamoa-Kakula demonstration garden, a key part of Kamoa Copper’s program to promote sustainable development.

Cannot view this image? Visit: https://i0.wp.com/orders.newsfilecorp.com/files/3396/95693_59685641249988fc_042.jpg?w=640&ssl=1



Mbangu Sangombe, one of the owners of the Katayi Community banana plantation.

Cannot view this image? Visit: https://i0.wp.com/orders.newsfilecorp.com/files/3396/95693_59685641249988fc_043.jpg?w=640&ssl=1


Princess Adèle Kayinda Mahina (centre), Minister of Portfolio, visiting a local primary school that is one of Kamoa
Copper’s community initiatives to increase education opportunities for families living near the Kamoa-Kakula Project.

Cannot view this image? Visit: https://i0.wp.com/orders.newsfilecorp.com/files/3396/95693_59685641249988fc_044.jpg?w=640&ssl=1



New community fish ponds constructed near the Kansoko Mine. Kamoa Copper recently initiated a catfish breeding program to further enhance food security and farming capacity in the host communities.

Cannot view this image? Visit: https://i0.wp.com/orders.newsfilecorp.com/files/3396/95693_59685641249988fc_045.jpg?w=640&ssl=1



Drilling rig in operation on Ivanhoe’s Western Foreland exploration licences near the Kamoa-Kakula Project.

Cannot view this image? Visit: https://i0.wp.com/orders.newsfilecorp.com/files/3396/95693_59685641249988fc_046.jpg?w=640&ssl=1


Ivanhoe’s Western Foreland, green horizons, blue sky.

About Ivanhoe Mines

Ivanhoe Mines is a Canadian mining company focused on advancing its three principal joint-venture projects in Southern Africa: the development of major new, mechanized, underground mines at the Kamoa-Kakula copper discoveries in the Democratic Republic of Congo and at the Platreef palladium-rhodium-platinum-nickel-copper-gold discovery in South Africa; and the extensive redevelopment and upgrading of the historic Kipushi zinc-copper-germanium-silver mine, also in the Democratic Republic of Congo.

Kamoa-Kakula began producing copper concentrates in May 2021 and, through phased expansions, is positioned to become one of the world’s largest copper producers. Kamoa-Kakula and Kipushi will be powered by clean, renewable hydro-generated electricity and will be among the world’s lowest greenhouse gas emitters per unit of metal produced. Ivanhoe Mines has pledged to achieve net-zero operational greenhouse gas emissions (Scope 1 and 2) at the Kamoa-Kakula Copper Mine when large-scale electric, hydrogen and hybrid underground mining equipment become commercially available. Ivanhoe also is exploring for new copper discoveries on its Western Foreland exploration licences in the Democratic Republic of Congo, near the Kamoa-Kakula Project.

Loading

Share this article on

Related posts

You have successfully subscribed to the newsletter

There was an error while trying to send your request. Please try again.

Copperbelt Katanga Mining will use the information you provide on this form to be in touch with you and to provide updates and marketing.