Zambia Cancels Zambezi Power Station Contract Over Cost and Procurement Issues 1Mining in Zambia Contracts & tenders Electricity 

Zambia Cancels Zambezi Power Station Contract Over Cost and Procurement Issues

Zambia has disclosed that it will cancel a building contract given to General Electric Co. and Power Building Corp. of China because the project to construct a 2,400-megawatt power station on the Zambezi River is excessively expensive.

In remarks aired last week on the state-run Zambia National Broadcasting Corp., and reported by the American news agency, Bloomberg, Zambia’s energy minister, Peter Kapala, noted that proper procurement procedures weren’t followed when the purchase was made.

The dam’s development is overseen by the state-run Zambezi River Authority, which predicted last year that the project would cost $5 billion.

“We are disengaging from that contract and we hope to re-advertise it and revisit everything that was agreed to before. Mainly, it was because of the cost, it was just too much,” said Kapala.

“The latest information is that the hydrology of Zambezi might not favor the establishment of a 2,400-megawatt hydro-plant,” the energy minister said.

“We could reach that if maybe we do a hybrid of solar and hydro itself, but the indications are that we could be looking at far much less than the 2,400, it could be maybe even 1,000 megawatts,” he added.

General Electric declined to respond right away. An email sent outside of regular business hours seeking comment did not immediately receive a response from PowerChina.

The 2,400-megawatt Batoka Gorge project was supposed to get going in 2020, however, there were a number of setbacks, including the coronavirus epidemic and problems obtaining finance.

General Electric and Power China were chosen to construct the facility jointly by Zambia and Zimbabwe. Both countries in southern Africa are experiencing an electrical shortfall as a result of poorly maintained plants and drought-related production reductions at existing hydroelectric facilities on the Zambezi River.

The secretary for energy and power development in Zimbabwe, Gloria Magombo, stated that she was not aware of the statements made by the minister of Zambia and that the ministry will reply later.

SOURCE:africa.businessinsider.com

Loading

Share this article on

Related posts

You have successfully subscribed to the newsletter

There was an error while trying to send your request. Please try again.

Copperbelt Katanga Mining will use the information you provide on this form to be in touch with you and to provide updates and marketing.