Manganese in SerenjeMining in Zambia 

ZCCM-IH’s Kabundi Resources Ltd commences manganese mining operations in Serenje

Works at the manganese mine in Serenje have commenced following the end of the heavy rains that had hampered kick-starting operations, posing a challenge in accessing the mine site areas.

ZCCM Investments Holdings Plc (ZCCM-IH) through its wholly-owned subsidiary Kabundi Resources Limited (KRL) are on-site and have started Phase one of the project in the small-scale mining license, with an initial capital injection of K18.6 million.

Phase two of the project which is scheduled to start before the onset of this year’s rainy season will be extended to other areas of the ZCCM-IH Large Scale Exploration area in Serenje.

ZCCM-IH Chief Executive Officer Mr. Mabvuto Chipata undertook a site visit end of April 2020, where he also inspected works at the Kampumbu Resettlement area earmarked for the relocation of nine (9) households from the Kabundi mine site.

The Resettlement Action Plan (RAP) approved by the Zambia Environmental Management Services (ZEMA) involves the construction of an additional one-by-two classroom block, a health center, nine-by-three bedroomed houses for the relocation of the Project Affected families, one house for a teacher, and another house for a medical staff.

These buildings will also be serviced and fully connected with piped water sourced from water boreholes to be drilled in the area.
Mr. Chipata was happy with the progress made both at the mining operation and the RAP sites.
He stated that the mine will be fully operational by July 2020, and looked forward to having it officially launched by August 2020.

ZCCM-IH will spend a total of K4.5 million to fulfill the RAP obligations, which are scheduled to be handed over to the beneficiaries in June 2020.

The RAP project has so far employed over 20 locals. KRL will further employ over 150 youths at the mine site as production scales up upon relocation of the affected families.
KRL targets to mine about 60,000 tonnes of manganese by the end of the year during the ramp-up period of operations.

Production is targeted to reach 240,000 tonnes of manganese ore annually once commercial production is achieved.
The Company is a strategic investment aimed at diversifying the commodity mix of the ZCCM-IH’s portfolio which is largely comprised of copper producing assets.

Share this article on

Related posts

You have successfully subscribed to the newsletter

There was an error while trying to send your request. Please try again.

Copperbelt Katanga Mining will use the information you provide on this form to be in touch with you and to provide updates and marketing.